    Construction update: Southwest BRT

    Crews are continuing their work at the northwest corner of 14 Street and 90 Avenue building the traffic detour. The pathway at the northwest corner of the intersection is currently closed until mid-April while crews finish building the traffic detour. Signs have been installed to inform pedestrians that the pathway is closed and how to access Glenmore Landing during this time.

    Work on installing temporary traffic lights at 14 Street/90 Avenue S.W. is underway, and crews will move to 14 Street/Heritage Drive S.W. next to install the permanent traffic lights. Crews will also be working along 14 Street and on 90 Avenue this week relocating utilities.

    What you can expect to see next:

    Once crews finish removing the concrete curbs at the 14 Street/90 Avenue S.W. intersection this week, they will be placing gravel on the north side of the intersection in preparation for paving the traffic detour. Crews will also start piling work for the underpass on the south side of the intersection in April, so residents can expect to see more equipment working in the area.

    Visit the website to see the intersection design during construction this year.

    Upcoming detours and lane closures:

    The bus stop on the north side of 90 Avenue S.W. has been moved to the west of the Glenmore Landing entrance closest to 14 Street S.W. Once crews are finished building the traffic detour at the intersection, the bus stop will be moved back to its original location.

    Lane closures will typically be between 9 a.m. and 3 p.m. For the upcoming week, expected closures and detours include:

    March 26 & 27, 2018 at 14 Street & 90 Avenue S.W.

    • Westbound 90 Avenue S.W. the right-hand lane will be closed from the intersection to just west of the merge lane to the first entrance of Glenmore Landing.

     March 26 – 29, 2018 14 Street between Southland Drive & 90 Avenue

    • Northbound 14 Street S.W. reduced to one lane between Southland Drive S.W. and 90 Avenue S.W.

      March 28, 2018 14 Street & 90 Avenue S.W.

    • Southbound right turn ramp from 14 Street S.W. onto 90 Avenue S.W. will be shifted onto a temporary asphalt lane. Drivers will use the temporary lane until the traffic detour is fully set up at the intersection in early April (see below).

    March 28 & 29, 2018 at 14 Street & 90 Avenue S.W.

    • Eastbound 90 Avenue S.W., reduced to two lanes, just west of 14 Street S.W.
    • Westbound 90 Avenue S.W., reduced to one lane (left-hand lane closed), just west of 14 Street S.W.
    • Northbound 14 Street S.W., reduced to two lanes (left-hand lane closed), just north of 90 Avenue S.W.

    Work happening in the next two weeks:

    This month and into the spring, crews will be focused on the 90 Avenue and 14 Street S.W. intersection. Trenching and piling is expected to start in April with ongoing work for temporary lighting and traffic lights.

     