    Construction update: Southwest BRT

    Crews are working on the excavation and piling for the underpass on the south side of 90 Avenue S.W.

    Utility relocations and work on street lights will continue along 14 Street S.W. and in the area around 90 Avenue S.W.

    Upcoming detours and lane closures:

    Lane closures are typically scheduled between 9 a.m. and 3 p.m.  

    April 30, 2018, 14 Street S.W. between Southland Drive & 90 Avenue S.W.

    • Northbound 14 Street S.W.: reduced to one lane (right-hand lane closed) for approximately 500 meters north of Southland Drive S.W.
    • Northbound 14 Street S.W.: reduced to one lane (left-hand lane closed) for approximately 800 meters south of 90 Avenue S.W. The left turn lane from 14 Street to 90 Avenue S.W. will be closed. Left turns will be permitted from left most lane.
    • Southbound 14 Street S.W.: reduced to one lane (left-hand lane closed) from Southland Drive S.W. to 90 Avenue S.W.

    May 1, 2018, 14 Street S.W. between Southland Drive & 90 Avenue S.W.

    • Northbound 14 Street S.W.: reduced to one lane (right-hand lane closed) for approximately 500 meters north of Southland Drive S.W.

    May 2 & 3, 2018, 14 Street S.W. between Southland Drive & 90 Avenue S.W.

    • Northbound 14 Street S.W.: reduced to one lane (left-hand lane closed) for approximately 800 meters south of 90 Avenue S.W.
    • Northbound 14 Street S.W.: reduced to one lane (right-hand lane closed) for approximately 500 meters north of Southland Drive S.W.
    • Southbound 14 Street S.W.: reduced to one lane (left-hand lane closed) from 90 Avenue S.W. to Southland Drive S.W. The left turn lane at 14 Street and Southland Drive S.W. will be closed. Left turns will be permitted from left most lane.

    May 3, 2018, Southland Drive S.W. & 14 Street S.W.

    • Eastbound Southland Drive S.W.: reduced to one lane (right-hand lane closed) from just west of the intersection to the bus bay
    • Westbound Southland Drive S.W. to northbound 14 Street S.W. right turn lane will be closed. Right hand turns will be permitted at the intersection.

    Work happening in the next two weeks:

    Crews will continue working on the piling and excavation for the underpass on the south side of 90 Avenue S.W. The detours above are for road work along 14 Street S.W. between Southland Drive and 90 Avenue S.W. that begin next week. Work includes removing the median on 14 Street to prepare for a traffic switch to the east side of 14 Street so crews can begin work on the west side of 14 Street.

    Crews will start road work at Southland Drive and 14 Street S.W. as well as north of Glenmore Trail in May. Road work on eastbound Glenmore Trail will include concrete and asphalt work, and shifting of travel lanes for an eastbound bus only lanes. Crews will also be starting work next month finishing the transit only ramp at the southeast corner of the Crowchild Trail and Glenmore Trail S.W. interchange.

     