    Construction update: Southwest BRT 

    Work continues on the south section of the vehicle bridge deck in preparation for shifting traffic to the second stage of the detour to enable the work on the north half of the vehicle bridge. The south underpass retaining walls are currently underway, as well as the piling for the underpass and excavation for the storm water pump station.

    Piling has been completed for the 90 Avenue S.W. pedestrian overpass in the northwest corner of the 90 Avenue and 14 Street S.W. intersection and piling on the east side of 14 Street S.W. is underway.

    Utility relocations and removals on the east side of 14 Street S.W. at the 90 Avenue S.W. intersection are ongoing.

    Work on the realignment of the trolley tracks at Heritage Park is now complete, and work on the overhead catenary system is expected to begin in January 2019.

    Residents living adjacent to areas where noise walls are proposed can expect a letter in the mail next week that shows where noise walls are being proposed and provides residents an opportunity to provide feedback on the future noise wall. Two-thirds of residents must vote ‘In Favour’ for the noise wall construction to proceed.

    There will be no construction activities during the week of December 24, 2018 for the holiday break.

    Upcoming detours & lane closures: 

    14 Street between Southland Drive & 90 Avenue S.W. – Underpass / Transitway / Pedestrian Bridge

    Monday, December 17, 2018  

    • 11:00 p.m. – 11:30 p.m.: Northbound and southbound 14 Street S.W. will be reduced to one lane in each direction. Flaggers will be on site to keep traffic moving as the piling rig moves across the street.
    • Southbound 14 Street S.W. reduced to one lane south of 90 Avenue S.W.
    • Northbound 14 Street S.W. reduced to two lanes north of 90 Avenue S.W. 

    Tuesday, December 18, 2018

    • Southbound 14 Street S.W. reduced to one lane south of 90 Avenue S.W.
    • Northbound 14 Street S.W. reduced to two lanes north of 90 Avenue S.W.
    • A section of eastbound 90 Ave reduced to two lanes west of 14 Street S.W.
    • A section of westbound 90 Ave reduce to one lane west of 14 Street S.W.

    Wednesday December 19 to Friday December 21, 2018

    • Southbound 14 Street S.W. reduced to one lane south of 90 Avenue S.W.
    • Northbound 14 Street S.W. reduced to two lanes north of 90 Avenue S.W.

    Upcoming work: 

    For the month of December, we will be minimizing construction along 14 Street to essential construction operations around the 14 Street S.W. and 90 Avenue S.W. area only and there will not be any major road closures.

    The second stage of the 90 Avenue underpass construction detour is expected to be implemented in early January 2019. This will involve shifting traffic lanes to the south, onto the new 90 Avenue vehicle bridge so crews can begin work on the north half of the underpass. 

    Heritage Park & Glenmore Landing businesses are open 

    Please note that both Heritage Park and the businesses at Glenmore Landing remain open throughout construction.

    Calgary Transit route changes 

    Transit riders are reminded to check out calgarytransit.com/routechanges for changes that came into effect on November 19, 2018.

     